6 | SM Split AH/AV Standard Package

SM SPLIT AH/AV STANDARD PACKAGE
Fig. 2 SM Split Series Water-to-Air Heat Pump Air Handler
[1] SM Split Series Water-to-Air Heat Pump Air
Handler
[2] Installation and Operation Manual

General Description

SM Split Series Water-to-Air Heat Pumps provide
the best combination of performance and
efficiency available. All units are performance
certified to American Heating and Refrigeration
Institute (AHRI) ISO Standard 13256-1. All SM
Water-to-Air Heat Pumps conform to UL 1995
standard and are certified to CAN/CSA C22.1 No
236 by Intertek-ETL.
Split system heat pumps consist of two
independently installed sections allowing for
centralized air distribution while remotely locating
the section containing the compressor and
water-to-refrigerant heat exchanger (Coax Water
Coil).
In the cooling mode, the air coil in the air handler
section serves as an evaporator and the water-to-
refrigerant heat exchanger serves as a condenser.
In the heating mode, their roles are reversed.
In cooling mode, the refrigerant lines connecting
the two sections consist of one line carrying liquid
refrigerant and another carrying refrigerant vapor.
The liquid carrying line will be referred to as the
liquid line while the vapor carrying line will be
referred to as the suction line.
8733826256 (2020/06)
The Water-to-Air Heat Pumps are designed to
operate with entering fluid temperature between
20°F to 80°F in the heating mode and between
50°F to 110°F in the cooling mode.
1
2

Moving and Storage

If the equipment is not needed for immediate
installation upon its arrival at the job site, it should
be left in its shipping carton and stored in a clean
and dry area. Units must only be stored or moved
in the normal upright position as indicated by the
"UP" arrows on each carton at all times.

Initial Inspection

Be certain to inspect all cartons or crates on each
unit as received at the job site before signing the
freight bill. Verify that all items have been received
and that there are no visible damages; note any
shortages or damages on all copies of the freight
bill. In the event of damage or shortage, remember
that the purchaser is responsible for filing the
necessary claims with the carrier. Concealed
damages not discovered until after removing the
units from the packaging must be reported to the
carrier within 24 hours of receipt.
Subject to change without prior notice
SM Split AH/AV Air Handler
Antifreeze solution is required for entering
fluid temperatures below 50°F. Reference
the installation and operational manual for
the SM Condensing Section for additional
details based on unit application.
NOTICE: This product should not be used
for temporarily heating/cooling during
construction. Doing so may effect the units