Installing a Chassis
Step 6
Push the chassis all the way onto the rack so that the vertical mounting brackets on the front of the chassis come in
contact with the vertical mounting rails on the rack.
Step 7
Use six M6 x 19 mm or 24 x 3/4-inch screws to attach each of the two chassis vertical mounting brackets to the two rack
vertical mounting rails (total of 12 screws). See Callout 2 in the following figure.
Figure 7: Attaching the Chassis to the Rack
1
Handles used to adjust the chassis
placement
What to Do Next
After you have secured the chassis to the rack, you can connect the chassis to the data center ground.
OL-30837-01
2
Six M6 x 19 mm or 10-24 x 3/4 in. Phillips screws used to attach each
side bracket to a front mounting rail (use a total of 12 screws)