Initial Inspections

7SJ62 Manual
C53000-G1140-C121-1
This section describes the first steps that should be taken upon receiving the
®
SIPROTEC
4 7SJ62.
Unpacking and packing is explained.
Visual and electrical checks that are appropriate for initial inspection are discussed.
The electrical tests include navigating through the operating menus of the device us-
ing the operator control panel on the front of the device, and the operator control win-
®
dows in DIGSI
4. For personnel inexperienced with the 7SJ62, these checks also
provide a quick and simple method for understanding the operation of the control pan-
®
el and DIGSI
4. The electrical tests can be done without measuring quantities being
applied.
Observations relevant to long-term storage of the device are noted.
3.1
Unpacking and Packing
3.2
Inspections Upon Receipt
3.3
User Interface
3.4
Storage
3
3-2
3-3
3-5