Operating limits and replacement intervals The recommended replacement intervals and the corresponding operating limits in chapter 3 are jointly defined with the enginebuilder. This information is specific to the product. Non-observance of the recommended replacement intervals and the operating limits increases the risk of unpre- dictable component failures.
Page 4
Introduction Purpose of the manual Operation Manual The Operation Manual explains the two-stage turbocharging (Power2) from ABB Turbo Sys- tems and contains instructions for safe operation. The Operation Manual is a complement to and expansion of existing national regulations for occupational safety, accident prevention and environmental protection.
Page 5
ABB Turbo Systems Ltd is identified as ABB Turbo Systems in this document. Official service stations of ABB Turbo Systems Official service stations are identified in this document as ABB Turbocharging Service Sta- tions. They are regularly audited and certified by ABB Turbo Systems. Also see chapter Con- tact information →8.
Page 7
Air or air/gas mixture inlet Air or air/gas mixture outlet and supply - - - Not included in the ABB Turbo Sys- to the charge air cooler tems scope of delivery The diagram shows the position of the low-pressure (Power2 LP) and high-pressure stage (Power2 HP) within two-stage turbocharging (Power2).
Page 8
Storage of new low-pressure and high-pressure stages and cartridge groups for up to 6 months New low-pressure and high-pressure stages and cartridge groups from ABB Turbo Systems can be stored in their closed packages for 6 months from the date of delivery without addi- tional mothballing measures (indicated by VCI label on package).
Page 9
Check the package for damage. If the package is damaged, the low or high-pressure stage or the cartridge group must be checked and repackaged by an ABB Turbocharging Service Station. After every 3 years, the following steps must be carried out by an ABB Turbocharging Service Station: ¡...
Page 10
Operation Manual / Power2 / 1 Introduction 1 Introduction / 1.6 Contact information Contact information Contact information for the ABB Turbocharging Service Stations is available online. Scan the QR code to access our website. ABB Turbo Systems Ltd Bruggerstrasse 71a...
Safety Introduction The two-stage turbocharging system (Power2) manufactured by ABB Turbo Systems is state of the art and complies with the respective health and safety standards in effect at the time the system was built. Thus Power2 is safe to operate. Nevertheless, there may be some re-...
This data is given on the rating plate and is gener- ally different for the low-pressure stage and high-pressure stage. ABB accepts no liability and rejects all warranty claims for any non-intended uses. [1]Euromot = The European Association of Internal Combustion Engine Manufacturers...
1 Safety / 1.6 Deflagration on gas engines Deflagration on gas engines Low-pressure stages from ABB Turbo Systems can tolerate a deflagration with a transient pressure increase of 12 bar (guideline value). High-pressure stages from ABB Turbo Systems can tolerate a deflagration with a transient pressure increase of 15 bar (guideline value).
The locations of the rating plates are defined in the Operation Manual, Chapter 4 Product description. Periodic check of the pressure vessels The pressure vessels used by ABB Turbocharging, such as those for wet or dry cleaning, are so-called "simple pressure vessels". ¡...
Power2 and can cause serious damage to property and injury to personnel. Only use original parts from ABB Turbo Systems. ABB Turbo Systems accepts no liability for any damage resulting from the use of non-ori- ginal parts and corresponding accessories.
Page 22
Non-insulated low-pressure and high-pressure stages can cause serious in- juries to personnel (burns). ABB Turbo Systems supplies the low-pressure and high-pressure stage with or without insulation in accordance with the purchase order received from the enginebuilder. If supply is without insulation, the enginebuilder is re-...
Page 35
Air or air/gas mixture inlet Air or air/gas mixture outlet and supply - - - Not included in the ABB Turbo Sys- to the charge air cooler tems scope of delivery The diagram shows the position of the low-pressure (Power2 LP) and high-pressure stage (Power2 HP) within two-stage turbocharging (Power2).
Page 37
Air or air/gas mixture inlet Air or air/gas mixture outlet and supply to - - - Not included in the ABB Turbo Sys- the charge air cooler tems scope of delivery The low-pressure stage (Power2 LP) is a turbomachine and consists of the main components turbine and compressor.
Page 39
Air or air/gas mixture inlet Air or air/gas mixture outlet and supply to - - - Not included in the ABB Turbo Sys- the charge air cooler tems scope of delivery The high-pressure stage (Power2 HP) is a turbomachine, and its main components are a tur- bine and a compressor.
Page 40
Figure 7: Locations of Power2 HP warning plates If warning plates are not present in the designated locations or not readable, proceed as follows: Order new warning plates from ABB Turbocharging Service Stations. Remove any warning plates that have become unreadable.
Page 48
NOTICE initial hours of operation. Continual escape of an oily fluid indicates a possi- ble oil leak. If there is a leak, contact an ABB Turbocharging Service Station. Commissioning after taking out of operation If present Remove cover plates (blind flanges) on the compressor casing, on the gas-inlet as well as ...
Page 49
necessary pressure assured at the oil inlet. For monitoring the lubricating oil pressure, ABB Turbo Systems recommends installing a ma- nometer "M". If the pressure is controlled electronically, the appropriate signals are to be trig- gered at the warning and alarm values.
Page 50
Table 6: Lubricating oil temperature at the outlet If the low or high-pressure stage was operated for a longer period of time outside of the ad- missible range, ABB Turbo Systems recommends to have the low or high-pressure stage in- spected by an ABB Turbocharging Service Station.
Page 52
If the engine can be stopped temporarily: Inspect air lines, exhaust gas pipes and the low-pressure and high-pressure stages and remedy any malfunctions. In any case, contacting the nearest ABB Turbocharging Service Station is recommended. 4.3.4 Malfunction of the speed measurement system The possible reasons for malfunction of the speed measuring system are described in chapter Troubleshooting / Speed measurement system [➙...
Page 54
Agree on a shortened service interval with ABB Turbo Systems. To prevent machine damage caused by ageing and downtime, we recommend having an in- spection carried out by an ABB Turbocharging Service Station no later than 5 years after the last service. 5.2.1 Service procedures every 25 …...
Page 55
Operation and service Page 23 / 59 5.2.4 Service work every 12000 ... 16000 hours of operation The rotor and bearing parts must be checked and assessed by an ABB Turbocharging Service Station. Dismantle low-pressure and high-pressure stage. Measure clearances. ...
Page 57
Compressor cleaning We recommend cleaning the HP compressor after the LP compressor. On V-engines with several low-pressure and/or high-pressure stages per engine, ABB Turbo Systems recommends the parallel cleaning of the LP compressors as well as the parallel cleaning of the HP compressors.
Page 59
ABB Turbocharging Service Station. The reduction of the engine load can lead to a reduction in the effectiveness of the compressor cleaning.
Page 60
Do not clean the compressors of the different high and low-pressure stages at the same time, but one after the other. On V-engines with several low-pressure and/or high-pressure stages per engine, ABB Turbo Systems recommends the parallel cleaning of the LP compressors as well as the parallel cleaning of the HP compressors.
Page 61
ABB Turbo Systems recommends using fuels with a mass ratio of vanadium to sodium of less than 3:1 so that the melting temperature of the sodium vanadyl vanadate is as high as possi- ble.
Page 62
Cleaning method and principle Cleaning of the turbine and the nozzle ring during operation is carried out by the cleaning method described in the following and is tested and approved by ABB Turbo Systems: Wet cleaning Wet cleaning makes use of various effects. These effects are used with varying levels of in- tensity, depending on the type of contamination: ...
Page 68
Have any heavily contaminated absorption segments and filter rings as well as damaged connecting rods replaced by an ABB Turbocharging Service Station. Fitting the filter silencer Assemble the insert units (E) by inserting the absorption segments (81136) into the sheet- ...
Page 71
To prevent significant loss of efficiency, specific tolerances must be fulfilled. If there is any doubt about the extent of the rubbing, contact an ABB Turbocharg- ing Service Station. Have a dimension check carried out by an ABB Turbocharging Service Station.
Page 72
Defects on the connected cylinders Contact enginebuilder High-pressure Heavy contamination of the turbine Clean stage Damaged rotor components or bearing Contact ABB Turbocharging Service Sta- tion Change of operating state of low- Check the operating point of the low- pressure stage pressure stage.
Page 73
Table 22: Malfunctions during operation – Power2 LP speed increases Increase in high-pressure stage speed Possible causes Remedy High-pressure Heavy contamination of the nozzle ring Contact ABB Turbocharging Service Sta- stage tion Low-pressure stage defective Contact ABB Turbocharging Service Sta-...
Page 76
Have the cause clarified and remedied immediately by an ABB Turbo- charging Service Station. Have parts assessed for damage and, if necessary, replaced by an ABB Turbocharging Service Station. Sporadic surge blows Surging of the low-pressure stage can occur during certain operating states, such as when reducing the engine performance quickly when manoeuvring.
If the acid number (TAN) is greater than 2 mg KOH/g, the following mothballing measures are necessary after taking the engine out of operation: Dismantle low-pressure and high-pressure stage The rotor and bearing parts must be dismantled and subsequently refitted by an ABB Turbocharging Service Station Clean all parts ...
Low-pressure and high-pressure stage remain attached to the engine. The casings of the low-pressure and high-pressure stage remain attached to the engine, the rotor and the bearing parts are dismantled by an ABB Turbocharging Service Station and stored separately.
Transport / weight Swivel lifting eyes to be used Two swivel lifting eyes (S) are required for the safe lifting of loads. These are not included in the ABB Turbo Systems scope of delivery. Swivel lifting eye (S) Power2 Thread...
ABB Turbo Systems recommends having further operations carried out only by trained staff or an ABB Turbocharging Service Station. Marking casing position for assembly ABB Turbo Systems recommends marking the casing positions prior to disassembly.
Page 104
Disassembly and assembly Page 12 / 49 Tightening torques for assembly devices Unless described otherwise, the screws and nuts of the assembly devices supplied by ABB Turbo Systems must be tightened so they rest firmly against the surface. Definition of terms ...
Serious damage to engines or property can be caused by clearances outside the tolerance and excessively worn parts. CAUTION Have the components assessed and, if necessary, replaced by an ABB Turbocharging Service Station. Figure 6: Measuring axial clearance A The axial clearance (A) must be measured prior to removal and after installation of the cartridge group.
Page 120
Remove and reinstall the cartridge group. Always replace jammed gasket rings with new ones. If the control dimension is still out of tolerance, contact an ABB Turbocharging Service Station. Figure 24: Measuring control dimension X After installing the cartridge group, the control dimension (X) must be measured.
Serious damage to engines or property can be caused by clearances outside the tolerance and excessively worn parts. CAUTION Have the components assessed and, if necessary, replaced by an ABB Turbocharging Service Station. Figure 28: Measuring axial clearance A The axial clearance (A) must be measured prior to removal and after installation of the cartridge group.
Page 132
Manufacturing the cover plate The cover plate and the other parts that are required are not included in the scope of delivery of ABB Turbo Systems and must be manufactured in accordance with the drawing (see Figure 32) by the operator.
Serial number of the low or high-pressure stage (PT……) Designation and part number. Spare parts can be ordered from an ABB Turbocharging Service Station. If different model variants are not taken into account in this document, contact an ABB Turbocharging Service Station.
Transport / weight Swivel lifting eyes to be used Two swivel lifting eyes (S) are required for the safe lifting of loads. These are not included in the ABB Turbo Systems scope of delivery. Swivel lifting eye (S) Power2 Thread...
(see Table 13: Tightening torques →27). Tightening torques for assembly devices Unless described otherwise, the screws and nuts of the assembly devices supplied by ABB must be tightened so they rest firmly against the surface. Definition of terms ¡ Suspension point Defined loading point on a component or an assembly (blind hole thread, eyelet, lug).
Clearances outside the tolerance Serious damage to engines or property can be caused by clearances outside the tolerance and excessively worn parts. Have the components assessed and, if necessary, replaced by an ABB Tur- bocharging Service Station. Fig. 13: Measuring axial clearance A The axial clearance (A) must be measured after removal and before installation of the cart- ridge group.
Page 171
The cover plate and the other parts that are required are not part of the scope of delivery of ABB Turbo Systems and must be manufactured by the operator on the basis of the drawing (see Fig. 24: Cover plate / gasket and sleeves →29).
Designation and part number. Spare parts can be ordered from an ABB Turbocharging Service Station. If different model variants are not taken into account in this document, contact an ABB Turbocharging Service Station. Dispose of placed and unusable parts in an environmentally-friendly and professional manner in accordance with the local regulations.