Cisco ONS 15600 SDH Manual
Hide thumbs Also See for ONS 15600 SDH:

Advertisement

Quick Links

Install the Bay and Backplane Connections
This chapter provides procedures for installing the Cisco ONS 15600 SDH. To view a summary of the
tools and equipment required for installation, see the
page

Before You Begin

This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).
Perform these procedures in the order they appear.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Only trained and qualified personnel should be allowed to install, replace, or service this equipment.
Warning
Statement 1030
November 2009
1-2.
NTP-F108 Unpack and Inspect the ONS 15600 SDH Bay Assembly, page
procedure before continuing with the
NTP-F109 Install the Bay Assembly, page
assembly.
NTP-F110 Install Additional Shelf Assemblies in the Bay (Two People), page
procedure to install up to two additional shelf assemblies in a bay.
NTP-F111 Open and Remove the Front Door, page
equipment before continuing with other procedures in this chapter.
NTP-F112 Install Cable Routing Modules and Kick Plates, page
remove the existing cable routers and install the cable routing modules (CRMs).
NTP-F113 Install the Bay Power and Ground, page
continuing with the
"NTP-F114 Remove the Rear Cover" procedure on page
NTP-F114 Remove the Rear Cover, page
"NTP-F115 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections" procedure on
page
1-12.
NTP-F115 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections, page
as needed to set up connections on the backplane.
NTP-F116 Replace the Rear Cover, page
NTP-F117 Perform the Bay Installation Acceptance Test, page
determine if you have correctly completed all other procedures in the chapter.
C H A P T E R
"Required Tools and Equipment" section on
"NTP-F109 Install the Bay Assembly" procedure on page
1-5—Complete this procedure to install the bay
1-7—Complete this procedure to access the
1-10—Complete this procedure before
1-11—Complete this procedure before continuing with the
1-13—Complete as needed to install the rear cover.
1-13—Complete this procedure to
Cisco ONS 15600 SDH Procedure Guide, R8.0
1
1-4—Complete this
1-6—Complete this
1-9—Complete as needed to
1-11.
1-12—Complete
1-5.
1-1

Advertisement

loading

Summary of Contents for Cisco ONS 15600 SDH

  • Page 1: Before You Begin

    C H A P T E R Install the Bay and Backplane Connections This chapter provides procedures for installing the Cisco ONS 15600 SDH. To view a summary of the tools and equipment required for installation, see the “Required Tools and Equipment” section on page 1-2.
  • Page 2 You will need the following tools and equipment to install and test the ONS 15600 SDH. Included Materials The ONS 15600 SDH bay ship kit is shipped with the ONS 15600 SDH. The under-floor power kit is an optional item and is used in environments where power is supplied through the floor, rather than overhead.
  • Page 3 – 8-32 flathead screws (10) – User-Supplied Materials The following materials and tools are required but are not supplied with the ONS 15600 SDH: Power cable, rated for at least 125-A capacity • • Ground cable, rated for at least 125-A capacity •...
  • Page 4 Visible laser source • Optical power meter • NTP-F108 Unpack and Inspect the ONS 15600 SDH Bay Assembly Purpose This procedure explains how to unpack the ONS 15600 SDH and verify the contents. Tools/Equipment Scissors Phillips screwdriver 3/4-inch (19.05 mm) socket wrench...
  • Page 5 1 1/8-inch (28.575 mm) socket 15/16-inch (23.8125 mm) socket Rectangular seismic washers (4) (53-2141-XX) 5/8-inch (15.88-mm) floor anchor bolts (4) Prerequisite Procedures NTP-F108 Unpack and Inspect the ONS 15600 SDH Bay Assembly, page Required/As Needed Required Onsite/Remote Onsite Security Level None This unit must be installed in a rack that is secured to the building structure.
  • Page 6 Connect the green ground wires, which were preinstalled, to the node. Step 7 Continue with the “NTP-F111 Open and Remove the Front Door” procedure on page 1-7. Step 8 Stop. You have completed this procedure. Cisco ONS 15600 SDH Procedure Guide, R8.0 November 2009...
  • Page 7 Note The ONS 15600 SDH has an ESD plug input and is shipped with an ESD wrist strap. One ESD plug input is located on the outside edge of the shelf on the left-hand side, and the other is located at the bottom rear of the shelf.
  • Page 8 “NTP-F112 Install Cable Routing Modules and Kick Step 5 Plates” procedure on page 1-9. If CRMs are already installed, continue with the “NTP-F113 Install the Bay Power and Ground” procedure on page 1-10. Cisco ONS 15600 SDH Procedure Guide, R8.0 November 2009...
  • Page 9 “DLP-F258 Replace the Existing 600-mm Kick Plates with 900-mm Kick Plates” task on page 17-51. If you want to install the wide CRMs, complete the “DLP-F277 Install the Wide CRMs” task on Step 4 page 17-65. Cisco ONS 15600 SDH Procedure Guide, R8.0 November 2009...
  • Page 10 DC circuit. To ensure that all power is OFF, locate the circuit breaker on the panel board that services the DC circuit, switch the circuit breaker to the OFF position, and tape the switch handle of the circuit breaker in the OFF position. Statement 140 Cisco ONS 15600 SDH Procedure Guide, R8.0 1-10 November 2009...
  • Page 11 Use copper conductors only. Statement 1025 Warning Always use the supplied ESD wristband when working with a powered ONS 15600 SDH. Plug the Caution wristband cable into either the ESD jack located on the lower-left outside edge of the bay assembly, or the other ESD jack located at the bottom rear of the shelf.
  • Page 12 Step 4 cables (or the RJ-45 port on the TSC) are required to access TL1. Always use the supplied ESD wristband when working with a powered ONS 15600 SDH. Plug the Caution wristband cable into either the ESD jack located on the lower-left outside edge of the bay assembly, or the other ESD jack located at the bottom rear of the shelf.
  • Page 13 ONS 15600 SDH Bay Installation Task Summary Description Completed NTP-F108 Unpack and Inspect the ONS 15600 SDH Bay Assembly, page 1-4 NTP-F109 Install the Bay Assembly, page 1-5 NTP-F111 Open and Remove the Front Door, page 1-7 Cisco ONS 15600 SDH Procedure Guide, R8.0...
  • Page 14 Chapter 1 Install the Bay and Backplane Connections NTP- F117 Perform the Bay Installation Acceptance Test Table 1-1 ONS 15600 SDH Bay Installation Task Summary (continued) Description Completed NTP-F112 Install Cable Routing Modules and Kick Plates, page 1-9 NTP-F113 Install the Bay Power and Ground, page 1-10...