hit counter script

Advertisement

Quick Links

Installing the Power Components
This chapter provides an overview of the AC and DC power systems and how to install the power modules
and input power cables into the Cisco NCS 6000 Fabric Card Chassis (FCC). For information about removing
power components, see the
Power System Overview
The Cisco NCS 6000 FCC can be configured with either an AC input power system or a DC input power
system. Site power requirements differ, depending on the source voltage used.
For information about power safety requirements, see the
the Cisco Network Convergence System 6000 Series Routers.
Prerequisites
Follow these precautions and recommendations when planning power connections to the FCC:
• Check the power at your site before installation to ensure that you are receiving clean power (free of
• Install proper grounding to avoid damage from lightning and power surges.
Installing the Fabric Card Chassis Ground Cable
The FCC has two safety earth ground connections. You can connect the central office ground system or interior
equipment grounding system to either of these grounding points on the rear side of the FCC. One chassis
ground is located near the top of the FCC and one chassis ground is located at the bottom of the FCC. These
Removing the Power Components
Power System Overview, page 1
Installing the Power Modules and Input Power Cables, page 11
Powering On and Powering Off the Fabric Card Chassis, page 23
spikes and noise). Install a power conditioner, if necessary.
Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide
section.
Regulatory Compliance and Safety Information for
1

Advertisement

Table of Contents
loading

Summary of Contents for Cisco NCS 6000

  • Page 1 Powering On and Powering Off the Fabric Card Chassis, page 23 Power System Overview The Cisco NCS 6000 FCC can be configured with either an AC input power system or a DC input power system. Site power requirements differ, depending on the source voltage used.
  • Page 2: Required Tools And Equipment

    Do not remove the FCC ground cable unless the FCC is being replaced. Required Tools and Equipment You will need to provide the following tools and equipment: • Number-2 Phillips screwdriver • Ground lug • Ground cable Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 3 • Two M6 bolts with integrated square cone locking washers (shipped pre-installed on the FCC, two at each grounding point). • 2-6-AWG multistrand copper ground cable. This cable is not available from Cisco; it is available from any commercial cable vendor such as Panduit (see http://www.panduit.com). The cable should be sized according to local and national installation requirements.
  • Page 4 Use the torque wrench to tighten the bolts to a torque of 30 in-lb (3.39 N-m). Step 4 Connect the other end of the ground cable to a grounding point at your site, according to site requirements. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 5: Overview Of The Ac Power System

    AC Power System Overview of the AC Power System An AC-powered Cisco NCS 6000 FCC contains four AC power trays that are part of the FCC power enclosure (Figure 1). The upper two power trays (PT0 and PT1) are referred to as PS0, and the lower two power trays (PT2 and PT3) are referred to as PS1.
  • Page 6 Installing the Power Components AC Power System (Cisco PID NCS-PDU-WYE) power interface, and has power input and power output cords entering and exiting the box. Figure 4: Cisco NCS-PDU Rack mounting ears Output cord Rack tray Two PDUs Input cord...
  • Page 7 Rack Mounting the AC PDU in a 19-Inch Rack). Figure 5: AC PDU Bracket Attached to the Side of the FCC AC PDUs (one each side) PDU bracket (chassis mount) Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 8: Installing The Tie-Down Bar

    A 19-inch tie-down bar can be used to add strain relief for input power cables from the AC PDUs or cables routed from a raised floor. The following figure shows holes for two 10-32 x 0.50 inch screws that are pre-drilled on the FCC for attaching a tie-down bar. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 9: Dc Power System

    Tie-down bar DC Power System A DC-powered Cisco NCS 6000 FCC contains four DC power trays that are part of the FCC power enclosure (Figure 1). The upper two power trays (PT0 and PT1) are referred to as power shelf 0 (PS0), and the lower two power trays (PT2 and PT3) are referred to as power shelf 1 (PS1).
  • Page 10 An “allpole” separation of the power source is not required. The DC PM is an isolated DC/DC converter Note with no galvanic connection between “L+” and the FCC. In addition, the “L+” potentials of each PM are isolated from each other. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 11: Installing The Power Modules And Input Power Cables

    Installing the Power Modules and Input Power Cables This section describes how to install the power modules and AC and DC power cables in the Cisco NCS 6000 FCC. We recommend that you perform the installation in the order outlined in this section.
  • Page 12: Installing An Ac Or Dc Power Module

    Installing an AC or DC Power Module This section describes how to install an AC or DC power module (PM) into the power trays in the Cisco NCS 6000 FCC. Although there are differences between the AC and DC PMs, they are installed by using the same procedures.
  • Page 13 LED. Figure 9: AC Power Module — Front View Figure 10: AC Power Module — Rear View Figure 11: DC Power Module — Front View Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 14 Do not install a power module into an AC or DC power tray until the power tray is securely screwed into the power enclosure. Required Tools and Equipment • ESD-preventive wrist strap • 6-inch, Number1 Phillips-head screwdriver Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 15 PM into PM0 in PT0 first. Next, install PMs in ascending order into the remaining PM bays in PT0. Then, install PMs in ascending order into the remaining power trays. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 16: About The Power Module Status Indicators

    • For DC power modules, the DC input LED lights up when the input voltage reaches within the acceptable range. • For AC power modules, the AC Input LED lights up when the input voltage reaches within the acceptable range. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 17 Figure 14: AC and DC Power Module Power Module Status Indicators Input OK LED Fault LED Output OK LED Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 18: Installing An Ac Or Dc Power Module Slot Cover

    Before performing this task, you must remove the cosmetic grilles and install the PMs to the required configuration in each power tray. Required Tools and Equipment • ESD-preventive wrist strap • AC or DC PM slot cover (Cisco PID A9K-PEM-V2-FILR) Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 19: Installing Ac Input Power Cords

    Ensure that there is a readily accessible disconnect device incorporated in the building's installation wiring. Before connecting AC input power cords to the power system, make sure that the input power cords are Caution not energized. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 20 The AC power system requires single-phase AC input power to each PM. If you have 3-phase AC Delta Note or AC Wye at your equipment, a Cisco NCS 6000 Series power distribution unit (PDU) is required to convert 3-phase AC input power to single-phase AC input power (Cisco PID NCS-PDU-DELTA or Cisco PID NCS-PDU-WYE).
  • Page 21: Installing Dc Input Power Cables

    The circuit breaker and fuse lockout procedures should follow the rules and regulations in the National Electrical Code (NEC) and any local codes. Required Tools and Equipment • DC power cables Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 22 • The resistance between the positive and negative power terminal studs of each input must be greater than 90 kohm. • The resistance between each positive terminal stud and bare metal surface on the power tray must be greater that 10 Mohm. Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 23: Powering On And Powering Off The Fabric Card Chassis

    Repeat these steps for all the power trays. Powering On and Powering Off the Fabric Card Chassis This section describes how to power on and power off an AC-powered or DC-powered Cisco NCS 6000 FCC. Powering On the Fabric Card Chassis Prerequisites •...
  • Page 24 Repeat Steps a through c for each of the remaining DC inputs. e) Continue to Step 5. Step 4 If you have an AC power system installed, follow these steps: Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...
  • Page 25: Powering Off The Fabric Card Chassis

    If the fault LED on any of the PMs are lit, we recommend that you replace the PM (see the Component Product for the Cisco PID). If the problem continues, please contact your Cisco support representative for assistance. Step 8 Install all cards in the FCC.
  • Page 26 Installing the Power Components Powering Off the Fabric Card Chassis Cisco Network Convergence System 6000 Fabric Card Chassis Hardware Installation Guide...

Table of Contents