Mounting a load cell with hygienic design

NOTICE
Observe the following points when mounting the load cell:
• Make sure that overloading of the load cell capacity is prevented at all times. If possible,
• Install the load cell in according with the instructions in the EHEDG documents 8 and 13.
• Mount the load cell in a self-draining orientation. Select the angle in such a way that liquids
• If welded adapters, mounting plates etc. are used, the surfaces coming into contact with
• Install the load cell in such a way that the first 100 mm of the cable protrude vertically from
Note
liquids.
• The screws required must correspond to EHEDG guidelines and have dome-shaped heads.
Adhere to the maximum tightening torque of the fixing screws. Technical specifications
(Page 69)
• To facilitate access for cleaning and inspection, the EHEDG guideline recommends a
minimum clearance of 300 mm between the device and the floor or wall.
SIWAREX WL200
Operating Instructions, 07/2024, A5E02199611B-14
install mechanical overload protection.
drain away completely through gravity alone.
food must have surface roughness of Ra ≤ 0.8 μm and the adapters must be WIG-welded.
You can find notes on welding in the EHEDG documents 9 and 35.
the cable gland so that the self-weight of the cable is carried and bending at the cable gland
is not possible.
Introduction of force can have an appropriate deflection angle, but not more than 5°.
The lower mounting plate must have a minimum bevel of 3° ~ 5° for the drainage of
4.3 Mounting a load cell with hygienic design