4.2 Commissioning with the IOP
The IOP is connected to the Inverter using an Optical RS232 cable. It will automatically
recognise the specific Control Unit to which it is connected, and displays only the parameters
and funtionality of the connected Control Unit.
What do you need?
The IOP Handheld Kit is a completed package that contains the necessary items to
commission and configure the Inverter utilizing the Optical Interface. The cable that is
delivered with the IOP Handheld kit is not compatible with the Optical Interface on the
G120D Inverters; the order details of the necessary cable is given below.
● The IOP Handheld Kit - order number: 6SL3255-0AA00-4HA0.
● Optical Cable - order number: 3RK1922-2BP00
Figure 4-1
CU240D-2 and CU250D-2 Optical Interfaces
4.2.1

Basic commissioning with IOP and P0015 Macros

Basic commissioning wizard (with P0015)
Note
Software limitations
The Basic Commissioning wizard detailed below is for Control Units with version 4.4
software or higher.
48
Getting Started, FW V4.5, A5E03404762A AB
Getting Started

Advertisement

Table of Contents
loading

This manual is also suitable for:

Sinamics cu250d-2Sinamics cu240d-2Sinamics pm250d

Table of Contents