Commissioning
5.3 Basic commissioning
5.3.5.3
Go online and start the configuration wizards - STARTER
Procedure with STARTER
Proceed as follows to start the quick commissioning of the inverter:
1. Select your project and go online:
2. In the following screen form, select the inverter with
which you wish to go online.
3. Download the hardware configuration found online in
your project (PG or PC).
Significance of the symbol in front of the inverter:
(A) The inverter is online.
(B) The inverter is offline
4. When you are online, double-click on "Control Unit".
5. Start the commissioning wizard:
You have started the quick commissioning of the inverter.
120
.
Distributed converter for SIMOGEAR geared motors
Operating Instructions, 06/2016, FW V4.7.6, A5E31298649B AG