1.1

Installation

Execute the following procedure to install the 7SR10 Overcurrent relay:
1.
Create a slot of dimensions as shown in Figure 1-2 to house the relay in the protection panel.
2.
Flush the rear-side of relay into the protection panel cut-out.
3.
Fasten the relay using the four M4x20 Pan Phillips SS screws with nut provided in the 7SR10 packing
box to the protection panel/cubicle.
4.
Carry-out all other installation steps/wiring internally from the protection panel.
5.
In the rear terminal of the relay, execute the wiring process as mentioned in scheme requirements.
Refer the diagram for more details about terminal connector diagram. Refer the table for the
recommended terminal lugs to be used.
6.
The earthing cable should be wired using a cable of 2.5 mm
the shortest possible path to the earth terminal/bus bar in panel or cubicle.
7.
Maintain a minimum clearance from the relay as given in Figure 1-1 to ensure safety and accidental
touch of terminals. In case of work area is restricted in a cubicle, then suitable protective terminals to
be provided in the cubicle.
NOTE:
The earthing point (E) of auxiliary supply is connected to the ground (GND) point of the relay. The earth
connection of relay casing should be solidly connected to the panel earth.
Figure 1-1
© 2018 Siemens Protection Devices Limited
2
Clearance for Terminal Wiring
7SR10 Installation Guide
(min) and this should be terminated in
25
25 mm clearance
for terminal wiring
Chapter 5 Page 3 of 13

Advertisement

Table of Contents
loading

This manual is also suitable for:

7sr1003 argus7sr1002 argus7sr1004 argus

Table of Contents

Save PDF