Required Tools For Installation; Required Parts For Installation - ABB ADC-90-200-C1 Operation And Installation Manual

All-in-one 90kw dc fast charger
Table of Contents

Advertisement

10.5

Required tools for installation

Parameter
Philips screwdriver
Slot screwdriver
Hex keys
Torx screwdriver
Torx angled or bit with
ratchet
Open spanner
Torque socket wrench
Ratchet spanner with
socket and extension
Voltage tester
Digital multimeter
Hoisting equipment or
forklift truck
Wire stripper pliers
Cable lug tool
10.6

Required parts for installation

Parameter
Swivel eye bolts or bolts with lifting
loops, to use with the hoisting equip-
ment
Cable lugs and fasteners
9AKK108466A3703-EN | 001
Specification
[mm]
Size: PH2
Size: 2.5 and 4.5
Size: 5, 5.5 and 6
Size: 15, 20 and 25
Size: 20
Size: M5 (8 mm), M6 (10
mm), M10 (15mm), M12 (19
mm) and M16 (24 mm)
5 to 20 Nm, size M8 (13
mm) and M6 (10 mm)
Size: M5 (8 mm) and M6
(10 mm)
Standard
To make sure that the RCD works, press the test but-
ton on the RCD.
Standard
Capable to lift the EVSE safely. Take into account the
dimensions, the mass, the center of gravity and the
maximum tilt angle. Refer to different sections in this
document.
To strip the wires of the AC input cable
Size: M10 (AC wires)
Size: M11 (PE wire)
Specification
Thread M10
Size: M10 (AC wires)
Size: M11 (PE wire)
Technical data
[in]
Size: PH2
Size: 0.1 and 0.18
Size: 0.2, 0.22 and 0.24
Size: 0.59, 0.79 and 0.98
Size: 0.79
Size: M5 (0.31 in), M6 (0.39
in), M10 (0.59 in), M12 (0.75
in) and M16 (0.94 in)
5 to 20 Nm, size M8 (0.51
in) and M6 (0.39 in)
Size: M5 (0.31 in) and M6
(0.39 in)
75